In Part-1 We Show Some Punch point In this we Know more Punch point.
Lets Know Following More Punch point
11) Battery Bank not grouted in Battery chiller (Shelter 1X1)
12) SMPS MCB (Y & B phase MCB) short by 10 sq mm instead of 16 sqmm & lugs not used.
13) Ac cut out not sealed properly.
14) Air gap found in shelter cut out below AC unit
15) DG automation not complete.
16) Earth chamber not found
17) EB Power MCCB 63 A used instead of 100 A.
18) AC Foundation otta plaster work not completed
19) Poll Mount not installed
20) Feature Expendable Ac MCB (ACDB-DCDB) supply cable connection not done.
21) OD cable trey grouting not done properly (pedestal done on ground level)
22) light & plug point cable connected with out lugs & Joint found in cable
23) Joint found in light & plug point cable.
24) Shelter cable entry hole not sealed.
25) Shelter (PIU) cable entry not sealed
26) SMPS MCB not working properly (80 A DC load MCB).
27) oint found in B cooler (AC)cable.
28) Remark :- LFL alarm not working ( Old DG)
29) SFU not installed.
30) Roxtec not available.
More Punch point See Part-3